SLEX Toll Road 4 (TR4) is a large-scale infrastructure project extending the South Luzon Expressway by 66.74 km from Santo Tomas, Batangas to Lucena City, Quezon. 



Designed as a four-lane toll road, it’s meant to ease congestion along the old Daang Maharlika (AH26) and cut travel time significantly—from 3–4 hours to approximately 45 minutes—1 hour.


Loading...

Route & Segmentation

The main alignment is divided into six construction packages:

  • TR4A: Santo Tomas → Makban (11.32 km)

  • TR4B: Makban → San Pablo (12.75 km)

  • TR4C: San Pablo → Tiaong (7.50 km)

  • TR4D: Tiaong → Candelaria (15 km)

  • TR4E: Candelaria → Tayabas (10.21 km)

  • TR4F: Tayabas → Lucena/Mayao (9.96 km)


It includes seven interchanges at Santo Tomas, Makban, San Pablo, Tiaong, Candelaria, Tayabas, and Lucena.




Project History & Timeline

Early planning dates back to early 2010s; construction officially began with a groundbreaking ceremony on March 26, 2019, by DPWH and SMC.

The project was initially set for completion in 2022 but faced delays due to right‑of‑way issues and pandemic disruptions.

As of January 2024, as-built progress varied per package: TR4A (~19%), TR4C (~62%), TR4D not yet started; overall right‑of‑way acquisition was ~93% complete.



Budget & Financing

Initial project estimates ranged from ₱13.1 billion to ₱26.1 billion, depending on the package.

SMC SLEX Inc. allocated:

  • ₱7.4 billion (2023) and ₱6.77 billion towards TR4 and SLEX widening.

  • Additional supplemental capex of ₱3.27 billion in 2024 — bringing total capex to ₱11.33 billion.

  • Plans to fully fund the ₱26.1 billion project by completion in 2026.




Construction & Current Status

Construction remains ongoing, with partial partial opening possible in 2025, while full operation is targeted for 2026—or possibly early 2027.

As of late 2024, some connected lanes along the existing SLEX are being widened to 6 lanes per direction, expected to complete by mid‑2025.

Supporting infrastructure, such as the Ayala Greenfield Interchange, began construction in October 2024, enhancing connectivity.


Strategic Importance

TR4 is a cornerstone of the national "Build, Build, Build" infrastructure initiative aimed at decongesting provincial roads and boosting regional mobility .

It's expected to reduce travel time from Sto. Tomas to Lucena from ~3 hours to ~45 minutes, transforming transportation for communities, tourism, and logistics.

It connects to upcoming SLEX TR5, which will extend further into the Bicol region, enhancing economic integration and trade routes.



Challenges & Concerns

Land acquisition hurdles delayed initial timelines—most right‑of‑way issues resolved by early 2024 .

Critics argue SLEX expansions—including TR4—are reactive, addressing traffic symptoms without fixing design flaws or flood resilience.

Drivers report pavement issues, poor signage, and RFID glitches on parts of the existing SLEX—a reminder of the need for quality controls as new sections come online.


Summary


SLEX TR4 represents one of the Philippines' most significant regional projects to date—promising transformative reductions in travel time, decongestion, and economic uplift for CALABARZON and beyond. Its success rests on timely completion, high-quality construction, and seamless integration with existing corridors. While minor challenges remain, the vision of a high-speed, efficient southern expressway is rapidly taking shape.


Where to Go in Quezon Province



IMPORTANT NOTE: The rates, contact details and other information indicated in this post are accurate from the time of writing but may change without IMFWJ's notice. Should you know the updated information, please let us know by leaving a message in the comment box below.

All You Need to Know About SLEX Toll Road 4 (TR4)


The closure of the southbound section of the EDSA-Kamuning flyover for six months starting May 1 will prompt motorists to explore additional alternate routes, as outlined by the Metropolitan Manila Development Authority (MMDA).



For drivers traveling from north EDSA or Caloocan, several options are available. Motorists can opt to turn right onto West Avenue, Panay Avenue, Mother Ignacia Avenue, Eugenio Lopez Jr. Drive, or Scout Borromeo, subsequently utilizing the MMDA Mabuhay Lane, which is outlined as follows:


Route 1
  1. From EDSA, turn right at West Avenue
  2. right at Quezon Avenue
  3. U-turn near Sct. Magbanua
  4. right at Timog
  5. right at Tomas Morato
  6. right at E. Rodriguez
  7. left at Gilmore
  8. straight to Granada
  9. right to Santolan Road or right at N. Domingo
  10. left at Pinaglabanan
  11. right at P. Guevarra
  12. left at L. Mencias
  13. right at Shaw Blvd.
  14. left at Acacia Lane
  15. right at F. Ortigas
  16. left at P. Cruz
  17. left at F. Blumentritt
  18. left at Coronado
  19. take Mandaluyong-Makati Bridge to destination




Route 2
  1. From EDSA, turn right at Panay Ave./Mother Ignacia Ave./Eugenio Lopez Jr. Drive/Sct. Borromeo
  2. left at Sct. Ybardolaza/Scout Torillo/Scout T. Morato/Scout Tuazon or Sct. Tobias
  3. right at E. Rodriguez
  4. follow the Mabuhay lane route 1 to destinations



Meanwhile, motorists on the east side of EDSA going southbound may use any of the following routes:


Route 1
  1. From East Ave, left at V. Luna Ave.
  2. right at Maliksi St.
  3. straight to K-H St., Cambridge
  4. right at New York Ave.
  5. left at Imperial
  6. straight to Gen. Aguinaldo Ave.
  7. right at P. Tuazon Ave., then exit to EDSA
  8. or straight to 8th Ave. to Col. Bonny Serrano, left towards C.P. Garcia Ave. (C5) or right towards EDSA to destination
 

Route 2
  1. From Kamias Road, right at K-H St., Cambridge
  2. right at New York Ave.
  3. left at Imperial
  4. straight to Gen. Aguinaldo Ave.
  5. right at P. Tuazon Ave. then exit to EDSA
  6. or straight to 8th Ave. to Col. Bonny Serrano, left towards C.P. Garcia Ave. (C5), or right towards EDSA to destination


ATTRACTIONS TO SEE IN MANILA 

Klook.com

Route 3

From Quezon Memorial Circle:

a)
  1. right at Kalayaan Ave.
  2. straight to K-J St.
  3. straight to Miami St.
  4. exit at Aurora Blvd.
  5. left at Gen. Aguinaldo Ave.
  6. right at P. Tuazon Ave. then exit to EDSA
  7. or straight to 8th Ave. to Col. Bonny Serrano, left towards C.P. Garcia Ave. (C5), or right towards EDSA to destination
 

b)
  1. from Kalayaan Ave./K-J St., right at Ermin Garcia Ave.
  2. left at 15th Ave.
  3. pass through Aurora Blvd./P. Tuazon Blvd./Main Ave. to Col. Bonny Serrano Ave.
  4. left towards C.P. Garcia (C5) or right towards EDSA to destination
 

c)
  1. from Kalayaan Ave., left at Matino St.
  2. straight towards Anonas Ext./Anonas
  3. right at Aurora Blvd.
  4. left at 20th Ave. to P. Tuazon Blvd./Col. Bonny Serrano Ave.
  5. left towards C.P. Garcia Ave. (C5) or right towards EDSA to destination
 

The MMDA announced on April 22 the closure of the EDSA-Kamuning flyover - southbound lanes starting May 1 to October 25 to undergo repair.

Only EDSA Carousel buses will be allowed to use the southbound lanes of the said flyover.

Here are the Alternate Routes for the Closure of EDSA-Kamuning Southbound

calax meaning calax update calax map cavite calax update 2021 calax rfid calax finish calax dpwh calax general trias

Going to Tagaytay has never been easier and faster until this expressway came into reality!



I was able to get to experience driving on CALAX for a few times when I recently had trips to Tagaytay with my friends. It was the real game-changer, easing the traffic flow in the busy Santa Rosa–Tagaytay Road which is usually used by many. 

CALAX Map

The Cavite–Laguna Expressway (CALAX or CALAEX) is a partially operational controlled-access toll expressway in the provinces of Cavite and Laguna, Philippines. The construction of the 44.63-kilometer-long (27.73 mi) expressway, which began in July 2019, costs an estimated ₱35.43 billion.

Loading...

Once completed, it will connect the Manila–Cavite Expressway in Kawit to the South Luzon Expressway in Biñan and is expected to ease the traffic congestion in the Cavite–Laguna area, particularly along the Aguinaldo Highway, Governor's Drive, and the Santa Rosa–Tagaytay Road.


CALAX begins at a roundabout at South Luzon Expressway's Greenfield City (Mamplasan) Exit in Biñan, continuing west then making a reverse curve to the southwest through the undeveloped private property owned jointly by Greenfield Development Corporation and Ayala Land, Inc.

It enters the Laguna Boulevard right of way near the boulevard's intersection with Greenfield Parkway. It approaches the first toll plaza near the Verdana Homes gated community, and continues southwest, passing through a mix of developed and undeveloped areas at barangays Loma and Timbao, then turning south into barangay Biñan, where it passes near Laguna Technopark, De La Salle University – Laguna Campus and several gated communities; access for them is provided by service roads that also serve as the southbound lanes of Laguna Boulevard.


The expressway partially runs above grade, utilizing underpass bridges, mechanically stabilized earth (MSE) walls and a viaduct at this section to pass above major intersections and accesses.

Entering Santa Rosa, CALAX descends into grade level to cross the Silang–Santa Rosa River and clear a power line, then gently curves to the southwest to follow the Nuvali Boulevard right of way, where the expressway ascends above grade again to pass over South Boulevard, served by the Laguna Boulevard Exit.


Past the exit, it leaves the Nuvali Boulevard right of way and crosses the Silang–Santa Rosa River once again, this time the Cavite–Laguna provincial boundary into Silang. It makes another reverse curve through cornfields and ends at the Santa Rosa City Exit, a trumpet interchange which leads to Santa Rosa–Tagaytay Road. A stub section is built west of the interchange, which will connect to the Cavite segment of the expressway.


The expressway continues southwest and makes a few turns before traversing a bridge and enters a cut section, passing near the Ayala Westgrove Heights. It turns northwest and passes under Tibig Road before ending at Silang East Exit, a diamond interchange which leads to Tibig-Kaong Road. A future road will be built west of the Silang East interchange that will connect to the Cavite segment of the expressway.

Cheapest Flights and Airline Tickets Online Booking

CONSTRUCTION

The first 8.9 kilometers (5.5 mi) of the expressway has been made accessible on October 30, 2019, in time for All Saints' Day and All Souls' Day. The entry and exit points at Mamplasan Interchange in Biñan, Laguna and Santa Rosa–Tagaytay Road were opened to serve an estimated 10,000 cars. According to DPWH Secretary Mark Villar, this will cut travel time from 45 minutes to just 10 minutes. However, the segment was supposed to be operational back in December 2018 or by February 2019.

The expressway was closed from January 28 to 31 and February 4 to 7, 2020 at 1:00 AM to 4:00 AM (PST) to give way for construction and clearing operations due to ashfalls brought by the 2020 Taal Volcano eruption.


On August 18, 2020, the Laguna Technopark and Laguna Boulevard Exits in Biñan and Santa Rosa, respectively, were opened to the public.


On August 24, 2021, the 6-kilometer (3.7 mi) section leading to the Silang East interchange in Silang, Cavite was opened to the public. However, this segment was supposed to be operational back in June 2021. Meanwhile, the section leading to the Silang interchange is expected to be completed in 2022.


CALAX EXITS

Exits will be numbered by kilometer posts, with Rizal Park in Manila designated as kilometer zero.





CALAX TOLL FEES

Cavite–Laguna Expressway is a closed road system, where motorists pay a toll rate based on the vehicle class and distance travelled. In 2020, motorists pay a fixed toll rate at their respective exit points when there were initially two operational toll barriers on the first 8.9-kilometer (5.5 mi) segment of the expressway:

cavite-laguna expressway update cavite-laguna expressway pnoy calax update 2022 calax general trias

Mamplasan and Santa Rosa City. The electronic toll collection (ETC) system on the expressway is operated by Easytrip Services Corporation and collections are done on mixed lanes at the toll barriers.

  • Class 1 (Cars, Motorcycles, SUVs, Jeepneys) - ₱64.00
  • Class 2 (Buses, Light Trucks) - ₱128.00
  • Class 3 (Heavy Trucks) - ₱192.00

In accordance with law, all toll rates include a 12% value-added tax.


Cavite–Laguna Expressway

Address: MPT South Hub - Alapan II-B, Imus, 4104 Cavite
Hotline: (02) 1-35000
Facebook Page: CALAX
Twitter Account: @OfficialCALAX



OTHER TOLLWAY / EXPRESSWAY IN PH


calax meaning calax update calax map cavite calax update 2021 calax rfid calax finish calax dpwh calax general trias  calax rfid calax toll calax meaning calax update 2022 cavite-laguna expressway update cavite-laguna expressway pnoy calax update 2022 calax general trias

Here are the latest news and updates from CALAX:

All you need know about Cavite-Laguna Expressway (CALAX)


A new milestone was reached by the Department of Public Works and Highways (DPWH) in the Davao City Bypass Construction Project with excavation works for the 2.3-kilometer twin tube road mountain tunnel now conducted at four (4) areas north and south portals. 

DPWH Undersecretary and Build Build Build Chief Implementer Emil K. Sadain together with Embassy of Japan in the Philippines Economic Affairs Minister Masahiro Nakata and Japan International Cooperation Agency (JICA) Chief Representative Takema Sakamoto led on June 9, 2022 the ceremonial kick-off of excavation activities for south portal tunnel southbound direction.

Undersecretary Sadain, in-charge of Unified Project Management Office (UPMO) Operations, explained that the road tunnel construction works using cutting-edge equipment and technologies were earlier started at north portal on November 19, 2021 for southbound direction and December 10, 2021 for northbound direction while excavation activities from opposite end at south portal northbound direction commenced last May 12, 2022. 

Loading...

Simultaneous tunnel portal construction activities on both ends will fast-track the completion of the soon to be first-ever long distance road mountain tunnel in the Philippines, Undersecretary Sadain said. 
Based on the report of Undersecretary Sadain to DPWH Acting Secretary Roger G. Mercado, construction of road tunnel at north portal has reached 202 meters at southbound and 91 meters at northbound.


The construction of road tunnel involves excavation of tunnel portal areas using the conventional "New Austrian Tunneling Method”, mucking or removal of soil from tunnel interior, initial shotcrete to protect from risk of fall materials and to prevent loosening during shotcrete application, steel ribs installation to provide effective structural protection, second shotcrete with wire mesh to secure stability, and rock bolt installation to provide bearing force and become a part of tunnel support system. 


The kick-off ceremony, following Filipino and Japanese traditions, at Barangay Matina Biao, Davao City was also attended by Councilor Edgar P. Ibuyan Jr. representing Davao City Mayor-elect Sebastian Z. Duterte; DPWH UPMO Roads Management Cluster 1 (Bilateral) Project Director Benjamin A. Bautista; Embassy of Japan 1st Secretary Jumpei Tachikawa; JICA Representative Ochi Kaoru; Davao City District Engineer Richard Ragasa; Project Managers  Joselito Reyes and Joweto V. Tulaylay; Engrs. Juan M. Diña Jr. and Earl Nicholas F. Rada; and officers of the consultants Nippon Koei Ltd., Katahira & Engineers International, Nippon Engineering Consultants Co., and PhilKoei International Inc.

The 45.5-kilometer Davao City Bypass Construction Project is divided into six (6) contract packages (CP) with the on-going CP 1-1 covering a 10.7 kilometers of 4-lane highway and 18.9 kilometers CP 1-2 and CP 1-3 under procurement stage financed by Official Development Assistance (ODA) from JICA thru the Special Terms for Economic Partnership (STEP) Loan Agreement Nos. PH-P261 and PH-P273.  While for funding by the Government of the Philippines are CP 2-1, CP 2-2 and CP 2-3 with a total length of 15.9 kilometers. 



The opening of new road networks through the Davao City Bypass Construction Project is expected to usher more development opportunities as it will greatly improve Davao City's accessibility and traffic condition.

“On behalf of DPWH, I would like to thank the Government of Japan thru JICA together with other development partners Asian Development Bank, World Bank, Export Import Bank of Korea, and Export-Import Bank of China for taking a great part in bolstering the Philippines’ stride to reach the peak of infrastructure development through the “Build, Build, Build” Program that will elevate living condition and benefit every Filipino”, added Undersecretary Sadain.


ATTRACTIONS TO SEE IN MANILA 

Klook.com

Other than the tunnel, CP 1-1 awarded to Shimizu – Ulticon - Takenaka  joint venture involves construction of four (4)-lane road with a length of 7.9 kilometers; three (3) pairs of bridges with total length of 500 meters including the Davao River Bridge; two (2) underpasses and two (2) overpasses; 12 waterways culverts; and four (4) at-grade intersection.

Starting from Davao-Digos section of the Pan-Philippine Highway in Brgy Sirawan, Davao City going to Davao-Panabo section of the Pan-Philippine Highway in Brgy J.P. Laurel, Panabo City, the project is expected to ease traffic situations along the areas.

The completion of the entire bypass road project will slash travel time to under 49 minutes from the usual 1 hour and 44 minutes.

Source: DPWH



DPWH works simultaneously on both ends of 2.3km Davao City Mountain Tunnel

Two (2) newly-completed parallel bridges built by the Department of Public Works and Highways (DPWH) now facilitate better mobility and connectivity in the province of Agusan del Sur.

Constructed along Daang Maharlika (Agusan-Davao Section), the 189-lineal meter Andanan Bridge in Bayugan City and the 125-lineal meter Gibong Bridge located in the municipality of Prosperidad provide wider developmental growth and increase efficiency in the delivery of basic services along the area.
Loading...

DPWH Secretary Roger G. Mercado lauded DPWH Regional Office 13 headed by Director Pol M. delos Santos and Assistant Director Abdulfatak A. Pandapatan for completing both projects earlier than the target date despite challengers due to COVID-19 restrictions and unfavorable weather conditions.
“The two permanent bridges provide a much wider perspective on inter-regional connections that will help maintain a continuous flow of traffic even with the increased volume of vehicles passing through the Agusan-Davao section of Daang Maharlika”, said Secretary Mercado.

Meanwhile, DPWH Regional Office 13 has programmed for immediate funding the completion of approaches of the two bridges.
Cheapest Flights and Airline Tickets Online Booking



Klook.com


Via DPWH

2 New Bridges Foster Inter-Regional Connectivity in Agusan Del Sur

laguna lakeshore expressway dike failed project laguna lake development project laguna lakeshore expressway dike open laguna lake reclamation project laguna lake flood control project laguna lake highway phase 2 calamba-los baños expressway

The Department of Public Works and Highways (DPWH) announced the start this December 2021 of the detailed engineering design (D.E.D.) for the proposed Laguna Lakeshore Road Network Project (LLRN).


This after DPWH Acting Secretary Roger "Oging" Mercado with Undersecretary for Unified Project Management Office (UPMO) Operations Emil K. Sadain; UPMO Roads Management Cluster 2 Project Director Sharif Madsmo H. Hasim; and Department Chief Accountant Mary Antoinette Z. Puno signed on November 22, 2021 the Consultant’s Services Contract for the D.E.D. of LLRN Project - Phase 1, a new road network at the western side of the Laguna Lake connecting Lower Bicutan, Taguig City and Calamba City, Laguna with a main alignment of 37.60 kilometers.


Loading...

This early, the millions of Filipinos are excited to witness and see how this new road project will change lives, said Secretary Mercado.

The parties to the contract agreement to conduct the D.E.D. are  Dr. Jovito Santos of Lead Consultant CTI Engineering International (CTII) Co., Ltd.; Junichiro Minobe of Chodai Co., Ltd.; Takashi Sato of Oriental Consultants Global Co., Ltd.; and Tenkoh Yoshida of Nippon Engineering Consultants Co., Ltd with CTII President & CEO Takahiro Mishina and DPWH UPMO Overall Project Manager for Asian Development Bank (ADB) Projects Soledad R. Florencio as witnesses.

These companies are first ranked joint venture firm in the procurement on August 25, 2021 of Consultancy Services for the D.E.D.


The ceremonial signing of Consultancy Contract was also attended by Country Director for the Philippines Mr. Kelly Bird and Southeast Asia Project Officer Mr. Shuji Kimura of ADB; LLRN Team Leader Project Manager Zenaida B. Mauhay; Project Manager Sol Abasa; and other officer of Associate Firms Angel Lazaro and Associates International, DCCD Engineering Corporation, TCGI Engineers, and KRC Environmental Services.


According to Undersecretary Sadain - President Rodrigo Roa Duterte’s designated Chief Implementer of Build Build Build (BBB) Program, the start of LLRN D.E.D. is another significant development in one (1) of the Department’s flagship infrastructure projects.

The LLRN Project will strengthen road transport efficiency towards Metro Manila and neighboring regions and will provide added opportunities to stakeholders -  more jobs will be created; traffic will be decongested; movement of goods and services will be a lot easier; and so much more benefits, said Undersecretary Sadain.



Under the contract agreement amounting ₱135.485 Million, the D.E.D. will be carried out for 15 months between December 2021 to February 2023. 


The D.E.D. will be funded by an additional financing of the ADB’s Infrastructure Preparation and Innovation Facility (IPIF) under loan number 3886-PHI.


Upon strong representation of DPWH-UPMO, LLRN Project was approved by the NEDA ICC - Technical Board on March 17, 2021, and by the NEDA ICC - Cabinet Committee on September 27, 2021. The project was approved by the NEDA Board through an Ad Referendum on October 18, 2021.
The Laguna Lakeshore Road Network Project - Phase I with a main alignment of 37.60 kilometer includes eight (😎 interchanges in Sucat, Alabang, Tunasan, San Pedro/Binan, Santa Rosa, Cabuyao, and Calamba.

Cheapest Flights and Airline Tickets Online Booking

This two-lane primary road consists of 11.80 km viaduct from Lower Bicutan to Muntinlupa, and 25.80 km combination of onshore viaduct and embankment from Muntinlupa to Calamba.


The project will also consider the planned developments introduced by various local government units along its proposed alignment.

It will feature an additional one (1) lane in each direction from Sucat, Muntinlupa to Sta. Rosa, Laguna; a cycling track and promenade from Tunasan, Muntinlupa to San Pedro, Laguna.

via DPWH
laguna lakeshore expressway dike failed project laguna lake development project laguna lakeshore expressway dike open laguna lake reclamation project laguna lake flood control project laguna lake highway phase 2 calamba-los baños expressway

READ MORE

DPWH to start Laguna Lakeshore Road Network Project in December

cllex map cllex update 2021 cllex toll fee cllex owner cllex google map cllex exits cllex operator cllex bike

The 18-kilometer portion of the new expressway, which covers the Tarlac, Rio Chico River Bridge and Aliaga sections, will benefit around 11,200 motorists and commuters.

It is also expected to shorten the travel time of 70 minutes between the cities of Tarlac and Cabanatuan to just 20 minutes.

Duterte said the event marks another milestone in his administration’s ambitious “Build, Build, Build” infrastructure program.

“This project will improve movement of goods going to and from Metro Manila and Central Luzon, which will be beneficial to entrepreneurs, consumers and the economy,” Duterte said in a keynote speech during the inauguration of the 18-kilometer Tarlac Interchange to Aliaga Section of CLLEX Project (Phase 1) in Tarlac City.

Loading...

He said the new expressway would also allow commuters to “spend more time for their families and other productive activities” since they need not endure a longer travel time.

“I am sure that our kababayans (fellow countrymen) will be pleased that the usual 70-minute travel between these two major cities in Central Luzon will be reduced to just 20 minutes,” he said. “This new expressway should greatly benefit commuters going to and from Metro Manila and Cabanatuan City with a shorter commute.”

Duterte also thanked the Japanese government for helping fund the construction of CLLEX in support of the Philippines’ “Build, Build, Build” program.

“The infusion of PHP12 billion by the Japan International Cooperation Agency or JICA attests to the indispensable role of Japan as one of our important partners in attaining inclusive program through infrastructure development,” he said.

Cheapest Flights and Airline Tickets Online Booking

Duterte likewise lauded the Department of Public Works and Highways (DPWH) and its partners for the “speedy, efficient, and timely” completion of the 18-kilometer section of the CLLEX.

He guaranteed his fellow Filipinos that his administration remains committed to fulfilling its promise of providing them a “more comfortable life.”

“And, this assurance includes the effective, efficient, safe and timely completion of major infrastructure and transportation-related developments,” Duterte said. “Just keep in mind that transparency, accountability and integrity must be upheld in all our development projects.”

Duterte also noted that the entire 30-kilometer CLLEX Project, once completed, will help improve access to several localities in Tarlac and Nueva Ecija.

The DPWH has promised to complete the entire 30-kilometer expressway project within Duterte’s term, with the 10.30-kilometer Cabanatuan Section under Contract Package 4 already at 88.7 percent completion.


OTHER INFRASTRUCTURE PROJECTS IN THE PHILIPPINES

 

via DPWH
cllex map cllex update 2021 cllex toll fee cllex owner cllex google map cllex exits cllex operator cllex bike

CLLEX opens its first 18km portion


This road will benefit many not only travelers but the locals of Quezon Province and nearby places. 

The Department of Public Works and Highways is about to fully complete its multi-year road widening project along Lucban-Majayjay Road in the municipality of Lucban, Quezon Province.


LOCALS BENEFIT FROM WIDENED LUCBAN-MAJAYJAY ROAD IN QUEZON PROVINCE 

DPWH Secretary Mark A. Villar said the road improvement project which was implemented since 2016 is now on its fiftth and final segment with only remaining works at a 260-meter section in Barangay Ayuti.

Loading...

“At present, motorists are reaping the benefits of a widened 3.32-kilometer portion of Lucban-Majayjay Road in Barangays Igang, Samil, and Ayuti,” said Secretary Villar.



With the completion of the entire project, locals and visitors alike will further enjoy an uninterrupted wide road passing through scenic rice fields.

It will further support the increasing influx of tourist arrivals in the Municipality of Lucban, Quezon and its adjacent towns and cities.

Lucban, Quezon tourism spots include Kamay ni Jesus Healing Church, Majayjay Falls, Mt. Banahaw, and Pahiyas Museum Art Center among others.

Cheapest Flights and Airline Tickets Online Booking

According to Senior Undersecretary for Luzon Operations Rafael C. Yabut, the 4.935 kilometers Lucban-Majayjay Road is one of the national highways that directly connects the provinces of Quezon and Laguna.

DPWH Quezon 1st District Engineering Office allocated a total of P149.75 Million for the Widening of Lucban-Majayjay Road in Lucban town, composed of P27.75 Million in 2016, P65 Million in 2017, P25 Million in 2018, P20 Million in 2019, and P12 Million in 2020.

Source: DPWH